Public Sector Network Tender Alert

 

26055-2013: UK-Belfast: Houses construction work

The competition is for 4 individual lots of mixed refurbishment and small new build works as follows:
Lot: 1 15 Massareene Gardens, Antrim.
Construction: Rehabilitation of 1 no. residential bungalow constructed circa 1980's.
End user: Complex Needs.
Mix: 5 no. 1P/1B units (Up to 25 m² each).
Estimated Construction Cost: GBP 59,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated/ Anticipated Completion: May/June 2013.
Estimated Construction Period: 3 months.
Contract: NEC3 Short Form.
Lot: 2 Nr Existing Satisfactory Purchases – Canal Street Newry.
Construction –:
(I) We wish to appoint a Contractor to undertake the upgrading works to 1 Nr existing property in Newry to provide 9 Nr. 1P/1B self-contained apartments
End user: Supported Housing – Young adults leaving/left care.
Mix: 9 Nr. 1P/1B Apartments.
Estimated upgrading Cost: Approx GBP 90 k.
Estimated/ Anticipated Start on Site: March 2013.
Estimated/ Anticipated Completion: May 2013.
Estimated Construction Period: 12 weeks.
Lot: 3 Drumalla Park Phase 2, Carnlough.
Construction: 7 General Needs Houses.
End user: General Needs.
Mix: 5 no 5P/3B houses (90/95 m²) and 2 no 3P/2B houses (60/65m²).
Estimated Construction Cost: GBP 620,000.
Estimated/ Anticipated Start on Site: February 2013.
Estimated Construction Period: 9 months.
Lot: 4 L'arche-Ormeau Rd, Belfast Refurbishment/Upgrading Works.
End user: Complex Needs.
Estimated Construction Cost: GBP 90,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated Construction Period: 2 months.

Ref: Minor Works Multi Lot.,

Contact:

Oaklee Homes Group
37-41 May Street
For the attention of: Ross McDonnell
BT1 4DN Belfast
UNITED KINGDOM
Telephone: +44 2890441356
E-mail: developmentprogramme@oaklee.org.uk
Further information can be obtained from: The above mentioned contact point(s)
Specifications and additional documents (including documents for competitive dialogue and a dynamic purchasing system) can be obtained from: The above mentioned contact point(s)
Tenders or requests to participate must be sent to: The above mentioned contact point(s)

Contract value: The competition is for 4 individual lots of mixed refurbishment and small new build works as follows:Lot: 1 15 Massareene Gardens, Antrim.Construction: Rehabilitation of 1 no. residential bungalow constructed circa 1980's.End user: Complex Needs.Mix: 5 no. 1P/1B units (Up to 25 m² each).Estimated Construction Cost: GBP 59,000.Estimated/ Anticipated Start on Site: March 2013.Estimated/ Anticipated Completion: May/June 2013.Estimated Construction Period: 3 months.Contract: NEC3 Short Form.Lot: 2 Nr Existing Satisfactory Purchases – Canal Street Newry.Construction –:(I) We wish to appoint a Contractor to undertake the upgrading works to 1 Nr existing property in Newry to provide 9 Nr. 1P/1B self-contained apartments.End user: Supported Housing – Young adults leaving/left care.Mix: 9 Nr. 1P/1B Apartments.Estimated upgrading Cost: Approx GBP 90 k.Estimated/ Anticipated Start on Site: March 2013.Estimated/ Anticipated Completion: May 2013.Estimated Construction Period: 12 weeks.Lot:3 Drumalla Park Phase 2, Carnlough.Construction: 7 General Needs Houses.End user: General Needs.Mix: 5 no 5P/3B houses (90/95 m²) and 2 no 3P/2B houses (60/65 m²).Estimated Construction Cost: GBP 620,000.Estimated/ Anticipated Start on Site: February 2013.Estimated Construction Period: 9 months.Lot: 4 L'arche-Ormeau Rd, Belfast Refurbishment/Upgrading Works.End user: Complex Needs.Estimated Construction Cost: GBP 90,000.Estimated/ Anticipated Start on Site: March 2013.Estimated Construction Period: 2 months.Estimated value excluding VAT: 860 000 GBP

Published: 25 Jan 2013, Receipt by: 1 Feb 2013